By L8MS Team · Updated 10 Nov 2026
BRS records two related things when monitoring does not go to plan:
- a nonconformity — a record that a check failed or did not happen;
- a remedial action — a piece of work needed to put something right, usually from a risk assessment or raised during a visit.
Types of nonconformity
- Nonconformities — a result outside its limits or a failed check (see Non-conforming results).
- Missed checks — the visit window closed with the test not done.
- Late entries — results entered after the window had closed.
- No access — the engineer could not get to the asset.
- Not required — the test was marked as not needed on that visit.
Nonconformities by type.
Risk and status
Each nonconformity has a risk from 0 to 4; 3–4 counts as high risk. It moves through the statuses your company has set up until it reaches one that signs it off. Signing off needs the sign-off permission on that site. Until then it is open.
Remedial actions carry two risks — LR (Legionella risk) and GR (general risk), 0 to 4 — a timescale to complete by, and the same kind of status.
Where to work on them