Nonconformities and remedial actions explained

BRS records two related things when monitoring does not go to plan:

  • a nonconformity — a record that a check failed or did not happen;
  • a remedial action — a piece of work needed to put something right, usually from a risk assessment or raised during a visit.

Types of nonconformity

  • Nonconformities — a result outside its limits or a failed check (see Non-conforming results).
  • Missed checks — the visit window closed with the test not done.
  • Late entries — results entered after the window had closed.
  • No access — the engineer could not get to the asset.
  • Not required — the test was marked as not needed on that visit.
The Nonconformities page with the type and risk figures along the top
Nonconformities by type.

Risk and status

Each nonconformity has a risk from 0 to 4; 3–4 counts as high risk. It moves through the statuses your company has set up until it reaches one that signs it off. Signing off needs the sign-off permission on that site. Until then it is open.

Remedial actions carry two risks — LR (Legionella risk) and GR (general risk), 0 to 4 — a timescale to complete by, and the same kind of status.

Where to work on them